From change trigger to final account. Times and approval limits are examples to adapt to the contract and Leader's delegation of authority.
- 1
Change identified
A change arises from a client or consultant instruction, revised drawing, RFI response, site condition, value engineering or programme change.
Project Manager / Site EngineerSame dayKey documentsSite instruction, drawing revision, RFI logControl ruleNo change is built or fabricated on verbal instruction alone.Oracle Fusion / AI agent supportAI agent compares new drawing revisions with the BOQ and flags affected items automatically. - 2
Notify and log
Give written notice to the client/consultant and log a VO number in the Variation Register.
Quantity SurveyorWithin 7 days (contract notice periods prevail, e.g. FIDIC claim notices within 28 days)Key documentsNotice letter, Variation RegisterControl ruleEvery change gets a VO number before any pricing.Oracle Fusion / AI agent supportFusion Project Management: change request logged against the project; agent drafts the notice letter. - 3
Assess scope and impact
Measure quantities, check design, materials, lead times, factory capacity and programme impact.
QS + Design Office + Production Planner2–5 daysKey documentsMark-ups, take-off sheets, programmeControl ruleAssess cost AND time; check effect on items already in production.Oracle Fusion / AI agent supportAgent extracts quantities from drawings/BOQ, checks open purchase orders and factory job cards in Fusion. - 4
Price the variation
Apply the rate hierarchy: (1) BOQ rate, (2) pro-rata BOQ rate, (3) new rate from Rate Build-up, (4) daywork.
Quantity Surveyor2–3 daysKey documentsRate Build-up, supplier quotes, daywork sheetsControl ruleUse the lowest applicable level of the hierarchy and keep the back-up.Oracle Fusion / AI agent supportAgent proposes the rate basis, pulls latest supplier prices from Fusion Procurement and drafts the build-up. - 5
Internal review and approval
Commercial review of price, margin and risk before submission, per approval limits.
QS Manager / Project Director / Commercial Director1–2 daysKey documentsVariation quotation, internal approval formControl ruleApproval limits in the table below; margin must not fall below target without sign-off.Oracle Fusion / AI agent supportFusion approval workflow routes by value; agent flags low-margin or high-risk VOs. - 6
Submit to client
Submit the variation quotation with drawings, quantities, rate build-up and time impact.
Quantity SurveyorWithin 14 days of noticeKey documentsVariation quotation + supporting documentsControl ruleOne submission per VO; track submission date.Oracle Fusion / AI agent supportAgent assembles the submission pack and tracks days pending. - 7
Negotiate and agree
Respond to queries, negotiate and obtain a signed Variation Order.
QS / Commercial DirectorTarget 14–21 daysKey documentsSigned VO, minutesControl ruleNo fabrication of high-value items before a signed VO, except urgent works under written site instruction.Oracle Fusion / AI agent supportAgent chases overdue approvals and drafts replies to consultant queries. - 8
Execute
Issue revised shop drawings, purchase orders and factory job cards; install on site.
Project Manager / ProductionPer programmeKey documentsShop drawings, POs, job cardsControl ruleChanges to POs and job cards reference the VO number.Oracle Fusion / AI agent supportFusion Procurement and Manufacturing / Projects updated; agent checks every PO line is tied to a VO. - 9
Update contract value and bill
Update the budget and revised contract sum; include approved VOs in the monthly payment application, with pending VOs shown separately.
QS / FinanceMonthlyKey documentsInterim payment application, Variation RegisterControl ruleBill only approved VOs as certified; report pending VOs to management.Oracle Fusion / AI agent supportFusion Project Billing and Contracts updated; agent prepares the monthly valuation and cash forecast. - 10
Close and final account
Reconcile all VOs in the final account; record lessons learned.
QS Manager / FinanceAt project completionKey documentsFinal account statementControl ruleNo open VOs at final account.Oracle Fusion / AI agent supportAgent reconciles VO values, invoices and receipts; summarises variation trends by client and consultant.
Approval authority (example – align with delegation of authority)
| Variation value (AED) | Approver |
|---|---|
| Up to 50,000 | QS Manager |
| 50,001 – 250,000 | Project Director |
| 250,001 – 1,000,000 | Commercial Director |
| Above 1,000,000 | General Manager |
KPIs to track
- —Variations as % of original contract sum
- —Average days from notice to signed VO
- —Value of unapproved work already executed (at risk)
- —Approved value vs submitted value (% recovered)
- —Margin on variations vs contract margin
API changes to the process (company-wide, shared by all projects)