Grand total incl. VAT
AED 4,954,172.21
Revised contract sum
AED 4,698,354.28
Saved

From change trigger to final account. Times and approval limits are examples to adapt to the contract and Leader's delegation of authority.

  1. 1

    Change identified

    A change arises from a client or consultant instruction, revised drawing, RFI response, site condition, value engineering or programme change.

    Project Manager / Site EngineerSame day
    Key documentsSite instruction, drawing revision, RFI log
    Control ruleNo change is built or fabricated on verbal instruction alone.
    Oracle Fusion / AI agent supportAI agent compares new drawing revisions with the BOQ and flags affected items automatically.
  2. 2

    Notify and log

    Give written notice to the client/consultant and log a VO number in the Variation Register.

    Quantity SurveyorWithin 7 days (contract notice periods prevail, e.g. FIDIC claim notices within 28 days)
    Key documentsNotice letter, Variation Register
    Control ruleEvery change gets a VO number before any pricing.
    Oracle Fusion / AI agent supportFusion Project Management: change request logged against the project; agent drafts the notice letter.
  3. 3

    Assess scope and impact

    Measure quantities, check design, materials, lead times, factory capacity and programme impact.

    QS + Design Office + Production Planner2–5 days
    Key documentsMark-ups, take-off sheets, programme
    Control ruleAssess cost AND time; check effect on items already in production.
    Oracle Fusion / AI agent supportAgent extracts quantities from drawings/BOQ, checks open purchase orders and factory job cards in Fusion.
  4. 4

    Price the variation

    Apply the rate hierarchy: (1) BOQ rate, (2) pro-rata BOQ rate, (3) new rate from Rate Build-up, (4) daywork.

    Quantity Surveyor2–3 days
    Key documentsRate Build-up, supplier quotes, daywork sheets
    Control ruleUse the lowest applicable level of the hierarchy and keep the back-up.
    Oracle Fusion / AI agent supportAgent proposes the rate basis, pulls latest supplier prices from Fusion Procurement and drafts the build-up.
  5. 5

    Internal review and approval

    Commercial review of price, margin and risk before submission, per approval limits.

    QS Manager / Project Director / Commercial Director1–2 days
    Key documentsVariation quotation, internal approval form
    Control ruleApproval limits in the table below; margin must not fall below target without sign-off.
    Oracle Fusion / AI agent supportFusion approval workflow routes by value; agent flags low-margin or high-risk VOs.
  6. 6

    Submit to client

    Submit the variation quotation with drawings, quantities, rate build-up and time impact.

    Quantity SurveyorWithin 14 days of notice
    Key documentsVariation quotation + supporting documents
    Control ruleOne submission per VO; track submission date.
    Oracle Fusion / AI agent supportAgent assembles the submission pack and tracks days pending.
  7. 7

    Negotiate and agree

    Respond to queries, negotiate and obtain a signed Variation Order.

    QS / Commercial DirectorTarget 14–21 days
    Key documentsSigned VO, minutes
    Control ruleNo fabrication of high-value items before a signed VO, except urgent works under written site instruction.
    Oracle Fusion / AI agent supportAgent chases overdue approvals and drafts replies to consultant queries.
  8. 8

    Execute

    Issue revised shop drawings, purchase orders and factory job cards; install on site.

    Project Manager / ProductionPer programme
    Key documentsShop drawings, POs, job cards
    Control ruleChanges to POs and job cards reference the VO number.
    Oracle Fusion / AI agent supportFusion Procurement and Manufacturing / Projects updated; agent checks every PO line is tied to a VO.
  9. 9

    Update contract value and bill

    Update the budget and revised contract sum; include approved VOs in the monthly payment application, with pending VOs shown separately.

    QS / FinanceMonthly
    Key documentsInterim payment application, Variation Register
    Control ruleBill only approved VOs as certified; report pending VOs to management.
    Oracle Fusion / AI agent supportFusion Project Billing and Contracts updated; agent prepares the monthly valuation and cash forecast.
  10. 10

    Close and final account

    Reconcile all VOs in the final account; record lessons learned.

    QS Manager / FinanceAt project completion
    Key documentsFinal account statement
    Control ruleNo open VOs at final account.
    Oracle Fusion / AI agent supportAgent reconciles VO values, invoices and receipts; summarises variation trends by client and consultant.

Approval authority (example – align with delegation of authority)

Variation value (AED)Approver
Up to 50,000QS Manager
50,001 – 250,000Project Director
250,001 – 1,000,000Commercial Director
Above 1,000,000General Manager

KPIs to track

  • —Variations as % of original contract sum
  • —Average days from notice to signed VO
  • —Value of unapproved work already executed (at risk)
  • —Approved value vs submitted value (% recovered)
  • —Margin on variations vs contract margin

API changes to the process (company-wide, shared by all projects)

0 change(s)
WhenActionRecord typeRecordWhat changed
The process has not been changed through the API yet.